2022 Overlays

  • Construction Year: 2022
  • Community: Throughout Scott County
  • Project Lead: Scott County
  • Contractor: McNamara Contracting, Inc.
  • Anticipated Completion Date: September 2022

Overlay Project (Updated 05/26/2022)

  • CH 27: From CH 44 to South Park Drive 

    • Location: Savage 
    • Work Description: Work includes removing the top 3 inches of bituminous, utility replacement, paving the top 3 inches with new bituminous, seal coating, ADA retrofits, and sign replacements. 
  • CH 79: From CH 10 to TH 282 (Spring Lake and Sand Creek Townships)

    • Location: Spring Lake and Sand Creek Townships 
    • Work Description: Work includes removing all existing bituminous, aggregate base cement stabilization, paving with 5 inches of new bituminous, sealcoating, and sign replacements.  
  • CH 16: From 410 Feet East of Phillip Drive 

    • Location: Shakopee 
    • Work Description:  The proposed work for this project includes removing an existing left turn lane and replacing it with a new concrete median. Also, as part of a development commitment, Scott County agreed to remove an existing left turn lane and median crossing along CH 16.  
  • Purpose & Justification

    This annual project is part of the Countywide pavement preservation program. Overlays are performed on a regular basis to preserve the initial paving investment and provide additional safety enhancements.  Please drive with caution.